Optimization of electricity transmission for a hotel chain

Optimize electricity transmission:

  • Identify savings on transmission cost items
  • Implement and monitor optimizations

Scope

  • Number of delivery points: 25
  • Annual consumption: 5 GWh
  • Annual transmission and tax expenses

Project timeline

  • Phase 1: Comprehensive collection of consumption data and detailed mapping of the scope
  • Phase 2: Site-by-site analysis and identification of optimizations
  • Phase 3: Presentation of optimizations to the client and site-by-site validation
  • Phase 4: Implementation of validated optimizations and follow-up until completion

Our added value and the results achieved

  • Central management of the project with handling and validation by each site manager
  • Internally developed tools enabling precise site-by-site analyses and real-time tracking of optimizations
  • Rigorous monitoring of deployment and availability in case of client requests: multiple suppliers to manage and engage
  • Recurring annual savings of 12 k€

 